| I. Annual Capital Budget |
Board
Projects greater than $2 million identified individually |
| II. Campus Master Plan |
Board |
| |
| 1. Less than $100,000 |
CFO/Provost |
| 2. $100,000 - $2,000,000 |
Capital Projects Committee |
| 3. $2,000,000 and over |
Requires Trustee Approval by Project |
| |
|
| Concept Development |
Capital Projects Committee |
| Program Plan |
Capital Projects Committee |
| Financing Plan |
Capital Projects Committee, Campus Planning and Facilities
Committee (Trustees) |
| Siting |
Capital Projects Committee, Campus Planning and
Facilities Committee (Trustees) |
| Architect Selection |
Capital Projects Committee, Campus Planning and Facilities
Committee (Trustees) |
| Schematic Design |
Capital Projects Committee, Campus Planning and Facilities
Committee (Trustees) |
| Budget Estimate |
Capital Projects Committee, Campus Planning and Facilities
Committee (Trustees), Financial Planning Committee (Trustees) |
| Financing |
Chief Financial Officer, Trustees |