Subject Area: Capital Planning and Budget Process
Responsible Office: Office of Facilities Services
Approval: V.P. for Administration and Chief Financial Officer
Originally Issued: March 2001
Revised: August, 2006
Refer Questions To: Donald Reaves
To establish the process for obtaining University approval for
construction, expansion, and renovation projects at various funding
request levels. The policy also defines project leadership roles during
the project phases of program development, design, and implementation.
Summary
- Any academic or administrative unit requesting central funding for
a project or proposing to spend $100,000 or more in unit funds on a
project shall submit a written description of the project and a project
budget to the Budget Office. The Budget Office approves projects under
$250,000. All projects involving space allocation must be submitted
to the Provost for approval no matter the funding level.
- Units proposing to spend between $250,000 and $1 million shall submit
a written description of the project and a project budget to the Budget
Office. The Budget Office will take the proposal to the Provost and
CFO for approval. The Provost and CFO will ask the Capital Projects
Committee (CPC) to review and approve if they feel the project has significant
impact on the University.
- Any academic or administrative unit contemplating a project greater
than $1 million, shall submit a written statement to the Provost explaining
the rationale for the contemplated project. Projects between $1 million
and $2 million are approved by the CPC. Projects of $2 million or more
are approved by the full Board of Trustees or the Executive Committee
of the Board of Trustees after review by the Campus Planning and Facilities
Committee (CPFC) or the Financial Planning Committee (FPC) or both.
If a project that was initially approved for less than $2 million ends
up over $2 million, the Board of Trustees will be notified of the scope,
budget, and description of the project.
- The Provost and CFO or the CPC, as appropriate, will provide written
authorization to complete the project's program development. The approval
memo will describe the scope of the project, the dollar amount required
for the programming and feasibility study, the schedule, and any conditions.
Program Development
- For projects that require a programming and feasibility study, Facilities
Services (FS) will lead program development, retain consultants and
work with the unit to prepare the study (or master plan or other work,
as appropriate).
- The programming and feasibility study will be reviewed by the CPC,
which will also review any space and campus plan considerations. If
appropriate, the Faculty Campus Planning Committee will be consulted
on the proposed project.
CPC Financial Plan Approval
- For approved projects, FS will develop and provide to the unit an
initial target budget for the project (renovation, expansion or new
construction). The unit will work with the Budget Office to develop
a financing plan that includes sources of revenue, timing of cash receipts,
borrowing assumptions, and other pertinent information. If fund raising
is part of the financing plan, the unit will submit the plan to the
Vice President for Development for a feasibility opinion.
Trustee Project Approval
- For approved projects with a total estimated project cost of $2 million
or more, the CFO will submit the project to the Financial Planning Committee
(FPC) and, if required, the Campus Planning and Facilities Committee
(CPFC) of the Board of Trustees for approval along with a request for
planning funds and an estimate of the total project cost. Once approved
by the FPC and the CPFC, if required, either the Executive Committee
or the full Board of Trustees also must approve the request.
Project Implementation - Design Phase
- If appropriate, after the project and planning funds have been approved,
the CFO will establish an Architect Selection Committee and Project
Steering Committee. The committees will include representative(s) from
the requesting unit, faculty, administrators, and trustees, as appropriate.
The Architect Selection Committee will search for and recommend an architect
for the project. The Project Steering Committee will play an advisory
role to the CFO and will review and make recommendations on major project
issues. FS will lead project implementation and will include unit representatives
on the project team to insure that unit needs are met and input is heard.
- Final architect selection requires approval by the CPFC.
- FS will negotiate with and sign the contracts with the design architect
and hire, negotiate with and contract with any additional consultants,
project managers, engineers, local architects, etc. necessary for the
project. FS will work in consultation with the Legal Office to negotiate
all contracts related to the project.
- The project team will submit the schematic design to the CPC for
approval (with the Faculty Campus Planning Committee advising the Provost),
and to any community hearings as appropriate. The schematic design,
along with an updated project cost estimate, will be submitted to the
CPFC for approval.
- Once the CPFC has approved the schematic design, FS will work with
the project team to complete design development.
- FS will provide cost estimates using either internal resources or
outside cost estimators throughout the process. FS will work with the
project team to bring the project in at budget. When disagreements exist
over budget, program or schedule priorities, FS will bring these issues
to the CPC or the Provost or CFO as appropriate, for resolution.
Project Implementation - Construction
- FS will follow Procurement Policy 1201 in the project procurement process. If construction of the project is
to go out to bid, FS will send it out to bid once design development
is complete, or at another phase in design if approved by the CFO and
CPC. Once the bids have been received, and a construction firm selected
from them, FS will submit a final total project cost to the CFO. This
final total project cost, if $2 million or more will require approval
by the CPC, the FPC, and either the full Board of Trustees or the Executive
Committee of the Board of Trustees before construction may begin.
- If permits or contracts are required, FS will obtain them before
construction begins. Requests to begin work before permits or contracts
are obtained must be approved by the Provost and CFO. The University
may allow some contractor activity to occur before a contract is signed,
but only through a letter of intent that will outline financial and
risk allocation between parties.
- FS will supervise the construction project, providing monthly updates
on major projects to the CFO who will keep senior management of the
University and the Executive Committee of the Board of Trustees informed
of their progress.
- FS will receive a three percent project management fee to fund its
work.
Project Implementation - Unit Withdrawal from a Project
- Units involved in a project but which choose to drop out of the project at any stage will be responsible for paying for the costs associated with programming, feasibility, planning, design, and construction which can be attributed to their specifications and are no longer applicable to the ongoing project. The unit will also be responsible for any additional costs incurred by the project as a result of its decision to drop out of the project. These could include costs associated with re-design, permitting, and the revision to or delay of the project schedule. The costs will be billed to the unit by the CFO and then reimbursed to the unit responsible for paying the costs of project implementation.
| Spending Approval Requirements |
| Project |
|
Approval Authority |
| I. Annual Capital Budget |
|
Capital Projects Committee (CPC) and Board of Trustees
Projects of $2 million or more are identified individually |
| II. Campus Master Plan |
|
Board of Trustees |
III. Individual Project Approval Levels |
| 1. Up to $100,000 |
|
Unit funded*-
Center funded- |
|
No approval required.
Budget Office approves. |
| 2. $100,000-$249,999 |
|
Unit or center funded- |
|
Budget Office approves. |
| 3. $250,000- $999,999 |
|
Unit or center funded- |
|
Budget Office takes proposal to CFO and Provost for approval.
CPC may review. |
| 4. $1,000,000- $1,999,999 |
|
Unit or center funded- |
|
CPC reviews. President, Provost and CFO approve. |
| 5. $2,000,000 and above |
|
Unit or center funded- |
|
The full Board of Trustees or the Executive Committee approves. |
*A unit can fund a project up to $100,000. Additions to the project
above that level will follow the approval levels listed above.
For center funded projects, a unit can add up to $100,000 of their funds
without approval. Adding additional unit funds requires approvals as
outlined above.
If funds are added to a project that put the total project budget into
the next level, the approvers of the next level will be given written
notification of the increase.
On all projects that are jointly funded by both the center and a unit,
unit funds will be spent first. Any funds remaining at the end of the
project will be returned to the center, up to its total contribution,
and then any remaining funds will be returned to the unit.
|